  1. Start with the opening, not the window
  2. Decide what you’re installing
  3. Measure and prepare before you start
  4. Step-by-step installation
  5. Common mistakes
  6. When to hire a professional
  7. Safety notes
  8. Bottom line

Start with the opening, not the window

Installing a wooden sash window is mostly about getting the opening right. The unit has to sit level, plumb and square, be fixed firmly, be sealed against water and air, and then have its sashes tested so they move freely and stay where you set them. Most problems with a new sash window trace back to one of those steps, so it pays to take each one slowly.

Decide what you’re installing

There are two common approaches:

  • A full window unit. The frame and sashes come as one assembly and are set into the opening. This is common when the old frame is rotten or when the old window is being removed completely.
  • New sashes in an existing frame. The moving sashes, and often a new balance system, are fitted into a frame that is still sound. This is less work when the frame is in good shape.

Check the frame before you choose. Press a screwdriver into the sill and the bottom of the sash box. If the wood is soft, crumbles or sinks in, the rot goes deeper than the paint and needs repair before any new window goes in. Houses from older periods often need a mix of both approaches, since the frame may be sound while the sashes or sills are not. If you are replacing wooden windows in an old house, expect some carpentry.

Measure and prepare before you start

Measure the rough opening. Measure the width at the top, middle and bottom, and the height at the left, middle and right. Check both diagonals and the depth of the opening. Measure the opening itself rather than the old window, since the old window may have been installed out of square. If you are unsure how to take these measurements, look up how to measure old wood windows for replacement before ordering. Order to the manufacturer’s sizing rules, which specify the gap they need around the unit.

Check the age of the house. Houses built before 1978 may have lead-based paint on the window frames and sashes. Test the paint before you sand, scrape or cut into it. If it contains lead, use lead-safe work practices, and consider a certified contractor if you are not sure how to proceed.

Gather your tools. You will usually need a drill and driver, a level, a tape measure, a square, shims, a utility knife, a putty knife, a pry bar, a caulk gun, safety glasses and gloves. Get a helper for lifting. A wooden sash with glass can be heavy and awkward to hold in place.

Plan the order of other work. Decide early whether the windows go in before or after the wall finish. Whether new windows or plaster first is the right sequence depends on how much of the wall you are opening up. Work out the timing with the weather barrier as well, since the window has to be flashed into it.

Step-by-step installation

Remove the old window

Protect the floor and nearby surfaces. Before you pry anything, score the paint line between the stops and the frame with a utility knife, so the paint doesn’t tear out with the wood.

Remove the interior stops, which are the thin strips that hold the sashes in place, along with any parting bead. Take out the lower sash first, then the upper one.

If the old window is weight-balanced, the cords or chains and the weights sit behind pocket covers in the frame. Remove the weights carefully and keep them labeled if you plan to reuse them. Cut the cords only after the sash is supported.

Whether you can keep the interior trim in place depends on the new unit’s size and on whether you are removing the whole frame. Often the trim has to come off, but in some jobs the new unit can be fitted without removing it. Look at both options before you start, since removing trim you didn’t need to remove means extra finish work later.

Inspect and prepare the opening

Look for rot, insect damage, water staining and loose framing. Repair what you find. A new window cannot fix a rotten opening, and the new unit will only hide the problem until it gets worse.

Check that the sill is level and the sides are plumb. Clear out old debris, dust and paint flakes so the unit has a clean surface to sit on.

Install sill protection, such as a sill pan or flexible flashing, following the manufacturer’s instructions. The job of that layer is to catch any water that gets past the window and send it back out.

Set the unit level, plumb and square

Dry-fit the unit in the opening before you fix anything. This shows you whether it fits and where it needs shims.

Place shims under the sill and at the sides to bring the unit level, plumb and square. Check both diagonals; they should match. Place shims close to where the fasteners will go, so the frame doesn’t bow when you drive them.

Do not force an out-of-square unit into an opening. If it doesn’t fit, check your measurements again or correct the opening. Forcing it can rack the frame, and a racked frame makes sashes stick.

Fasten the frame

Fix the frame through the jambs into the framing, using the fasteners the manufacturer specifies. Keep fasteners out of the sash channels and balance pockets, where they could catch a sash or a cord.

Tighten in stages and check the sashes as you go. If a sash starts binding when you tighten a screw, loosen it and adjust the shims.

Seal and flash the exterior

Fill the gap between the frame and the rough opening with a low-expansion window foam, applied sparingly. Standard expanding foam can push the frame out of square, so check the product label. Where the instructions call for backer rod and sealant instead, follow them.

Integrate the flashing with the wall’s weather barrier so that water runs out over each layer, the way shingles overlap. Whether windows go in before house wrap has no single answer. It depends on the wall system and the flashing details, so follow the window maker’s instructions and plan the overlap before the unit goes in. Use an exterior-rated sealant at the joints where the instructions call for it.

Set the balances and test the sashes

Operate each sash through its full travel. It should move smoothly, without binding, and stay where you put it.

For cord-and-weight windows, reattach the cords and check that the weights don’t bottom out in the pockets or catch on the pulleys. If a sash is too heavy or too light, retie the cords and test again. For spring balances, follow the manufacturer’s adjustment instructions, since the springs are under tension.

Install the stops last, and check that they don’t pinch the sashes. Test the locks and any lifting handles.

Finish the trim and paint

Fit the interior casing and trim, caulk the joints, and fill the nail holes. Then paint or finish the wood, starting with the exposed end grain. Choose a paint designed for wood windows, and follow the manufacturer’s guidance on priming and the number of coats. Keep paint out of the sash channels and the meeting rails, or the sashes may stick later.

Common mistakes

  • Shimming too little, or in the wrong places, so the frame is pulled out of square when fastened.
  • Using standard expanding foam, which can bow the frame.
  • Leaving out the sill flashing, or getting the flashing overlap wrong so water runs behind the unit.
  • Driving fasteners through a sash channel or balance pocket.
  • Finishing the trim before testing the sashes. Fixing a sticking sash after the trim is on is much harder.
  • Painting the sashes shut.

When to hire a professional

Consider a contractor when the window is heavy or historic, when there is lead paint, when rot extends beyond the sill, when the framing needs changing, when the window is on an upper floor, or when a broken cord or weight is involved and you are not sure how to replace it safely.

Ask for a written quote that says whether removal, disposal, sill repair and trim are included. Quotes that look similar can cover very different work.

Safety notes

  • Use a helper to lift and set heavy units. Keep your fingers out of the gap while the unit is lowered into the opening.
  • If a sash cord has broken, the sash can drop quickly. Don’t reach into the channel while the sash is hanging free.

Bottom line

Measure the opening carefully, prepare it, set the unit level, plumb and square, and fasten it without distorting the frame. Then seal and flash the exterior, test the sashes, and finish the trim and paint. Testing before the trim goes on is the step most often skipped, and it is the one that saves the most rework.