Short answer
In most renovations, the windows go in before the plaster is finished. The fitter sets the frame and seals it, and then the plasterer works up to the frame. That order keeps the opening closed while the rest of the work goes on, and it avoids cutting back plaster that has already been finished.
Plaster can go on first, too. That order is common when the windows have a long lead time, but it usually means more repair work once the windows arrive.
Why windows first is the common order
Three reasons come up most often:
- Weather. An open window hole lets in rain, wind and cold. Closing it early protects the new plaster and the rest of the room while the work continues.
- Less making good. If the plaster is already on the wall, the fitter has to chip back the plaster around the opening. The plasterer then has to come back to finish the edge. Each extra visit adds dust, drying time and cost.
- A cleaner edge. A plasterer can work the plaster right up to a fitted frame, so there is no gap to bridge later.
When plaster first makes sense
Plastering first can work well in a few cases:
- Long lead times. Some windows take weeks to arrive, and the plaster schedule may not wait for them.
- A plasterer who finishes the opening. The plasterer can finish the edge of the opening with a bead, so the window can be fitted into a neat edge later.
- A tight schedule. The plastering and decorating can go ahead while the windows are still being made.
Expect extra work with this order. The fitter may need to cut back plaster, the frame needs protecting from dust and splatter, and someone will need to make good the wall afterward. Ask who does that work and who pays for it before the job starts.
Measure before you order
The size of the opening can change once the plaster goes on, because the plaster adds thickness at the edges. Measure again once the wall is finished or the plaster date is set, and always before you order. Openings are rarely perfectly square, so measure the width and height at more than one point. For more on this step, see how to measure old wood windows for replacement.
Windows and house wrap in new construction
In new construction, the bigger question is the weather barrier. Windows can go in before or after the house wrap, as long as each layer is flashed so water runs outward. In both sequences, the sill pan goes in before the window. The article on whether windows go in before house wrap covers this in more detail.
A sequence that works for most renovations
- If you are replacing a window, remove the old one and check the opening for rot, damage or a failing sill.
- Fix any structural or moisture problems before the new window goes in.
- Set the window, seal it and fit it according to the maker’s instructions.
- Plaster or drywall the surrounding wall, finishing at the frame.
- Fit the interior sill and trim, then paint.
If the existing trim is staying in place, the order can change. See can windows be replaced without removing trim for that case. If the wall is stucco, the order matters even more, so check should you remediate stucco or replace windows first before you set the schedule.
Questions to ask your builder or fitter
- Who fits the windows, and who finishes the plaster?
- What is the lead time for the windows, and can they be on site before the plaster is due?
- Who protects the frames from plaster dust and splatter?
- Who makes good the wall, and is that cost in the quote?
If you plan to fit the windows yourself, it helps to know what the job involves. Is it hard to replace your own house windows covers the skills and tools most people need.
Check local rules
Building codes and inspection rules vary by area. Some inspections have to happen before walls are closed up, so the order you choose may need to fit the inspection schedule. Check with your local building department before you set the order of work. Always follow the window maker’s installation instructions, since they set out the sealing and flashing details.
Bottom line
For most renovations, windows go in first and the plaster follows. This keeps the opening closed and cuts down on repair work. Plastering first is a workable option when windows arrive late, as long as you plan for the extra making good and measure carefully. Timing the work around the season can also affect the cost, so see what is the cheapest time of year to replace windows if you have some flexibility.